Microwave Power Transmission Studies Vol4 of 4

Cover 1
Title Page 3
Table of Contents (Vol IV - Sections 9 through 14 with Appendices H through K) 11
Section 9 Reveiving Antenna 22
9.1 Microwave Rectifier Technology 22
9.2 Antenna Approaches 30
9.3 Topology of Rectenna Circuits 35
9.4 Assembly and Construction 42
9.5 ROM Cost Estimates 42
9.6 Power Interface Estimates 46
9.6.1 Inverter System 51
9.6.2 Power Distribution Costs 51
9.6.3 System Cost 52
9.7 Conclusions and Recommendations 52
References (Section 9) 53
Section 10 Frequency Interference And Allocation 56
10.1 Noise Considerations 58
10.1.1 Amplitron 58
10.1.2 Klystron 59
10.1.3 Interference Limits and Evaluation 61
10.2 Harmonic Considerations 61
10.3 Conclusions and Recommendations 67
Section 11 Risk Assessment 68
11.1 Technology Risk Rating and Ranking 68
11.2 Technology Assessment Conclusions and Recommendations 83
Section 12 System Analysis And Evaluation 86
12.1 System Geometry 86
12.2 Parametric Studies 88
12.2.1 System Relationships 88
12.2.2 Efficiency, Weight and Cost 93
12.2.3 Converter Packing 97
12.2.4 Capital Cost Vs Power and Frequency Results 98
12.2.5 Ground Power Density and Power Level Selection 104
12.2.6 Frequency Selection 107
12.2.7 Characteristics of 5 GW and 10 GW Systems 107
12.2.8 Energy Cost 121
12.3 Final System Estimates 126
12.3.1 Cost and Weight 126
12.3.2 Efficiency Budget 128
12.3.3 Capital Cost and Sizing Analyses 130
12.4 Conclusions and Recommendations 130
Section 13 Critical Technology And Ground Test Program 134
13.1 General Objectives 134
13.2 Detailed Ground Test Objectives 135
13.3 Implementation - Ground Test 136
13.3.1 Summary 136
13.3.2 Phase I 138
13.3.3 Phase II 138
13.3.4 Phase III 142
13.3.5 Alternate Phase I Converter Implementation 144
13.4 Critical Technology Development 147
13.4.1 Amplitron 147
13.4.2 Klystron 147
13.4.3 Phase Control 147
13.5 Schedule and Cost 148
13.6 Conclusions and Recommendations 150
Section 14. Critical Technology And Orbital Program 152
14.1 Orbital Test Objectives 152
14.2 Implementation 154
14.2.1 Geosatellite (Mission 1) 155
14.2.2 Shuttle Sorties (Missions 2 through 11) 155
14.2.3 Orbital Test Facility 174
14.3 Cost and Schedule 176
14.4 Conclusions and Recommendations 181
Appendix H: Estimated Annual Operations And Maintenance Cost 182
Appendix I: Annual Operations And Maintenance Cost 184
Appendix J: System Analysis Examples 186
J.1 Introductory Analysis of Initial Operational System With Minimum Size Transmitting Antenna 186
J.2 Analysis of the Final Operational System and Their Goals 195
J.3 Analysis of the Initial Operational System Based On the Final System Configuration 206
J.4 Weight and Cost Analysis for the Initial and Final Operational Systems 208
J.5 Energy Cost 212
Appendix K: Details Of Ground And Orbital Test Program 220
K.1 Introduction 220
K.2 Objectives Implementation Equipment and Characteristics 220
K.3 Implementation of Objectives H2, H2, DI and D2 Using Low Earth Orbit Sortie Missions 222
K.4 Defining an MPTS Orbital Test Facility Program 232
K.4.1 Assumptions 232
K.4.2 Sizing the Phased Array Antennas 233
List of Illustrations 15
Figure 9-1. Microwave Rectifier Device Technology 24
Figure 9-2. Chronology of Collection and Rectification of Microwave Power 26
Figure 9-3. Major Rectenna Development Programs 27
Figure 9-4. Simplified Electrical Schematic for the Rectenna Element 28
Figure 9-5. Rectenna Element Efficiency Vs Frequency 29
9-6 Comparison of Antenna Approaches in Meeting Requirements for Reception and Rectification in Space-to-Earth Power Transmission 9-U 15
Figure 9-7. DC Power from Center and Edge Rectenna Elements as Function of Rectenna Dia and Total dc Power Received 33
Figure 9-8. Rectenna Element Efficiency as Function of Microwave Power Input 34
Figure 9-9 Microwave Losses in an Optimally Designed Diode as a Function of Input Power Level for a Microwave Impedance Level of 120 Ohms 36
Figure 9-10. Losses at Low Values of Microwave Power Input 37
Figure 9-11. Schematic Arrangement of Rectenna 38
Figure 9-12. Full-Wave Configuration 40
Figure 9-13. Bridge-Rectifier Configuration 40
Figure 9-14. Full-Wave and Bridge-Rectifier Configurations in Relationship to Wave Filter Terminals 40
Figure 9-15. Pseudo Full-Wave Two-Conductor Rectifier 41
Figure 9-16. Rectenna Construction 43
Figure 9-17. Rectenna Elements 44
Figure 9-18. Approach to Environmental Protection of Rectenna Elements 45
Figure 9-19. Industry Accumulated Production Experience (Billions of Units) 47
Figure 9-20. High Speed Rectenna Production 48
Figure 9-21. Basic Rectenna Distribution Layout 49
Figure 9-22. Estimated dc-ac Interface Losses 50
Figure 9-23. Inverter Unit Cost Derivation 51
Figure 9-24. Power Distribution ROM System Cost 51
Figure 9-25. Total Power Interface ROM Cost 52
Figure 10-1. RF Spectrum Utilization 57
Figure 10-2. Estimated Noise Power Density at Earth 60
Figure 10-3. MPTS Ground Power Densities for Harmonics 66
Figure 11-1. Technology and Hardware Development Risk Rating Definition 68
Figure 11-2. Satellite Power System Technology Risk Assessment 69
Figure 12-1. MPTS Geometry 87
Figure 12-2. MPTS Functional Diagram 89
Figure 12-3. Beam Efficiencies (ng) for Truncated Gaussian Tapers 92
Figure 12-4. MPTS Efficiency (n) vs Frequency for Parametric Studies 95
Figure 12-5. Parametric Study Specific Costs and Weights 96
Figure 12-6. SPS Capital Cost vs Frequency - 300 $/kg 99
Figure 12-7. SPS Capital Cost vs Frequency - 100 $/kg 99
Figure 12-8. Transmitting Antenna Diameter for Lowest Cost SPS 100
Figure 12-9. Receiving Antenna Minor Axis for Lowest Cost SPS 101
Figure 12-10. Transmitting Antenna Diameter for Lowest Cost SPS (300 $/kg, 500 $/kW) 102
Figure 12-11. Receiving Antenna Minor Axis for Lowest Cost SPS (300 $/kg, 500 $/kW) 103
Figure 12-12. SPS Capital Cost for Klystron Configurations 105
Figure 12-13. Peak Ground Power Density vs Frequency 106
Figure 12-14. Receiving Antenna Size vs Beam Efficiency and Taper 108
Figure 12-15. Transmitting Antenna Size Vs Beam Efficiency and Taper 109
Figure 12-16. Peak Ground Power Density vs Beam Efficiency and Taper 110
Figure 12-17. Cost Matrix - 5 GW - Case LMM 112
Figure 12-18. Cost Matrix - 5 GW - Case MMM 113
Figure 12-19. Cost Matrix - 5 GW - Case LLH 114
Figure 12-20. Cost Matrix - 5 GW - Case HHL 115
Figure 12-21. Cost Matrix - 10 GW - Case LMM 116
Figure 12-22. Cost Matrix - 10 GW - Case MMM 117
Figure 12-23. Cost Matrix - 10 GW - Case LLH 118
Figure 12-24. Cost Matrix - 10 GW - Case HHL 119
Figure 12-25. Amplitron-Aluminum MPTS Comparison 120
Figure 12-26. Comparison of 5 GW Systems 120
Figure 12-27. SPS Capital Cost for Various Power Source Characteristics 125
Figure 12-28. SPS Energy Cost for Various Power Source Characteristics 125
Figure 12-29. SPS Energy Cost for Various Rates of Return 125
Figure 12-30. SPS Energy Cost for Various Construction Cycles 125
Figure 12-31. MPTS Cost Matrix 127
Figure 12-32. MPTS Efficiency Budget 129
Figure 12-33. Summary of Initial and Final Operational System Characteristics 131
Figure 13-1. MPTS Ground Test Functional Block Diagram 137
Figure 13-2. Instrumentation System Block Diagram 139
Figure 13-3. Ground Test Program Array Characteristics 140
Figure 13-4. Phase II Subarray - 2 x 2M - 40 kW 141
Figure 13-5. Received Power Density 142
figure 13-6. Candidate Location for Phase III Demonstration 143
Figure 13-7. Phase III Rectenna 144
Figure 13-8, Phase III Received Power 145
Figure 13-9. MPTS Ground Test Siting Profile Phase III - Goldstone 146
Figure 13-10. Technology Development and Ground Test System Schedule 149
Figure 14-1. Microwave Orbital Program 156
Figure 14-2. Geosatellite Concept 157
Figure 14-3. Five Kilowatt Geosatellite Payload 157
Figure 14-4. Geosatellite Weight Estimate and Predicted Interim Upper Stagv Performance and IUS Performance Estimate 158
Figure 14-5, Mission Schedule 159
Figure 14-6(a). Mission 2 - Structural Fabrication Technology 161
Figure 14-6(b). Mission 2 - Test Matrix 161
Figure 14-7(a). Mission 3 - Joint and Fastener Technology- 163
Figure 14-7(b). Mission 3 - Test Matrix 163
Figure 14-8(a). Mission 4 - Waveguide Fabrication Technology Sortie 165
Figure 14-8(b). Mission 4 - Test Matrix 165
Figure 14-9(a). Mission 5 - Electronics Integration 166
Figure 14-9(b). Mission 5 - Test Matrix 166
Figure 14-10(a). Mission 6 - Subassembly Build-Up 168
Figure 14-10(b). Mission 6A - Test Matrix 168
Figure 14-ll(a). Mission 7 - Rotary Joint Assembly 169
Figure 14-11(b). Mission 7 - Test Matrix 169
Figure 14-12(a). Mission 8 - Antenna to Rotary Joint Interface 171
Figure 14-12(b). Mission 8 Test Matrix 171
Figure 14-13(a)» Mission 9 - Central Mast Assembly and Integration Test 172
Figure 14-13(b). Mission 9 - Test Matrix (Conducting Mast Assembly) 172
Figure 14-14. Mission 11 - Test Matrix 175
Figure 14-15. OTF Antenna 175
Figure 14-16. OTF Power Densities 176
Figure 14-17 MPTS Orbital Test Program ROM Costs(Rough Order of Magnitude in Millions of 1975 Dollars)(Page 1 of 2) 178
Figure 14-18. Critical Technology Schedule 180
Figure 14-19. MPTS Orbital Test Program ROM Cost Summary (Rough Order of Magnitude in Millions of 1975 Dollars) 180
J-1 Total Cost Summary Format 187
J-2 Total Cost Summary - Initial Operational Systems With Minimum A(T) 189
J-3 Total Cost Summary - Operational System (Goal) 196
Figure J-4 Total Cost Summary - Initial Operational System Using 207
Figure J-5. Summary of Initial and Final Operational System Characteristics 214
Figure J-6. Capital Cost to Energy Cost Conversion versus Rate of Return 215
Figure J-7. SPS Capital Cost/ Transportation Cost for Various Power Source Characteristics 216
Figure J-8. SPS Energy Cost/Transportation Cost for Various Power Source Characteristics 217
Figure J-9. SPS Energy Cost/Transportation Cost for Various Rates of Return 218
Figure J-10. SPS Energy Cost/Transportation Cost for Various Construction Cycles 219
Figure K-l. Summary of Ground Test Objectives/Implementation 221
Figure K-2. Ionospheric Effects 223
Figure K-3. Utilization of Arecibo to Accomplish Ionosphere Test Requirements 223
Figure K-4. Ionosphere Test Requirements for F Layer 223
Figure K-5 . Power Subarray Assembly Options for Meaningful Orbital Tests 224
Figure K-6. Recommended Microwave Payload Assemblies Build-Up 224
Figure K-7 Critical Technology Required for Defined Microwave Power Ground and Orbital Test Program (Sheet 1 of 5) 225
Figure K- 8. Configurations to be Investigated on Orbit (Subarray and Below) 230
Figure K-9. Development Configuration (Subarray and Below Incorporating Control and Support Equipment) 231
Figure K-10. Large Array and Subarray Sizes for Cost. Inertia and Performance Estimation Purposes 235
Figure K- 11 Array Flight Test Hardware 241
Figure K-12. Summary of Altitude Range and Associated Power Densities 242
List of Non-Standard Terms 20

RkJQdWJsaXNoZXIy MTU5NjU0Mg==