1
245
Microwave Power Transmission Studies Vol4 of 4
Cover
1
Title Page
3
Table of Contents (Vol IV - Sections 9 through 14 with Appendices H through K)
11
Section 9 Reveiving Antenna
22
9.1 Microwave Rectifier Technology
22
9.2 Antenna Approaches
30
9.3 Topology of Rectenna Circuits
35
9.4 Assembly and Construction
42
9.5 ROM Cost Estimates
42
9.6 Power Interface Estimates
46
9.6.1 Inverter System
51
9.6.2 Power Distribution Costs
51
9.6.3 System Cost
52
9.7 Conclusions and Recommendations
52
References (Section 9)
53
Section 10 Frequency Interference And Allocation
56
10.1 Noise Considerations
58
10.1.1 Amplitron
58
10.1.2 Klystron
59
10.1.3 Interference Limits and Evaluation
61
10.2 Harmonic Considerations
61
10.3 Conclusions and Recommendations
67
Section 11 Risk Assessment
68
11.1 Technology Risk Rating and Ranking
68
11.2 Technology Assessment Conclusions and Recommendations
83
Section 12 System Analysis And Evaluation
86
12.1 System Geometry
86
12.2 Parametric Studies
88
12.2.1 System Relationships
88
12.2.2 Efficiency, Weight and Cost
93
12.2.3 Converter Packing
97
12.2.4 Capital Cost Vs Power and Frequency Results
98
12.2.5 Ground Power Density and Power Level Selection
104
12.2.6 Frequency Selection
107
12.2.7 Characteristics of 5 GW and 10 GW Systems
107
12.2.8 Energy Cost
121
12.3 Final System Estimates
126
12.3.1 Cost and Weight
126
12.3.2 Efficiency Budget
128
12.3.3 Capital Cost and Sizing Analyses
130
12.4 Conclusions and Recommendations
130
Section 13 Critical Technology And Ground Test Program
134
13.1 General Objectives
134
13.2 Detailed Ground Test Objectives
135
13.3 Implementation - Ground Test
136
13.3.1 Summary
136
13.3.2 Phase I
138
13.3.3 Phase II
138
13.3.4 Phase III
142
13.3.5 Alternate Phase I Converter Implementation
144
13.4 Critical Technology Development
147
13.4.1 Amplitron
147
13.4.2 Klystron
147
13.4.3 Phase Control
147
13.5 Schedule and Cost
148
13.6 Conclusions and Recommendations
150
Section 14. Critical Technology And Orbital Program
152
14.1 Orbital Test Objectives
152
14.2 Implementation
154
14.2.1 Geosatellite (Mission 1)
155
14.2.2 Shuttle Sorties (Missions 2 through 11)
155
14.2.3 Orbital Test Facility
174
14.3 Cost and Schedule
176
14.4 Conclusions and Recommendations
181
Appendix H: Estimated Annual Operations And Maintenance Cost
182
Appendix I: Annual Operations And Maintenance Cost
184
Appendix J: System Analysis Examples
186
J.1 Introductory Analysis of Initial Operational System With Minimum Size Transmitting Antenna
186
J.2 Analysis of the Final Operational System and Their Goals
195
J.3 Analysis of the Initial Operational System Based On the Final System Configuration
206
J.4 Weight and Cost Analysis for the Initial and Final Operational Systems
208
J.5 Energy Cost
212
Appendix K: Details Of Ground And Orbital Test Program
220
K.1 Introduction
220
K.2 Objectives Implementation Equipment and Characteristics
220
K.3 Implementation of Objectives H2, H2, DI and D2 Using Low Earth Orbit Sortie Missions
222
K.4 Defining an MPTS Orbital Test Facility Program
232
K.4.1 Assumptions
232
K.4.2 Sizing the Phased Array Antennas
233
List of Illustrations
15
Figure 9-1. Microwave Rectifier Device Technology
24
Figure 9-2. Chronology of Collection and Rectification of Microwave Power
26
Figure 9-3. Major Rectenna Development Programs
27
Figure 9-4. Simplified Electrical Schematic for the Rectenna Element
28
Figure 9-5. Rectenna Element Efficiency Vs Frequency
29
9-6 Comparison of Antenna Approaches in Meeting Requirements for Reception and Rectification in Space-to-Earth Power Transmission 9-U
15
Figure 9-7. DC Power from Center and Edge Rectenna Elements as Function of Rectenna Dia and Total dc Power Received
33
Figure 9-8. Rectenna Element Efficiency as Function of Microwave Power Input
34
Figure 9-9 Microwave Losses in an Optimally Designed Diode as a Function of Input Power Level for a Microwave Impedance Level of 120 Ohms
36
Figure 9-10. Losses at Low Values of Microwave Power Input
37
Figure 9-11. Schematic Arrangement of Rectenna
38
Figure 9-12. Full-Wave Configuration
40
Figure 9-13. Bridge-Rectifier Configuration
40
Figure 9-14. Full-Wave and Bridge-Rectifier Configurations in Relationship to Wave Filter Terminals
40
Figure 9-15. Pseudo Full-Wave Two-Conductor Rectifier
41
Figure 9-16. Rectenna Construction
43
Figure 9-17. Rectenna Elements
44
Figure 9-18. Approach to Environmental Protection of Rectenna Elements
45
Figure 9-19. Industry Accumulated Production Experience (Billions of Units)
47
Figure 9-20. High Speed Rectenna Production
48
Figure 9-21. Basic Rectenna Distribution Layout
49
Figure 9-22. Estimated dc-ac Interface Losses
50
Figure 9-23. Inverter Unit Cost Derivation
51
Figure 9-24. Power Distribution ROM System Cost
51
Figure 9-25. Total Power Interface ROM Cost
52
Figure 10-1. RF Spectrum Utilization
57
Figure 10-2. Estimated Noise Power Density at Earth
60
Figure 10-3. MPTS Ground Power Densities for Harmonics
66
Figure 11-1. Technology and Hardware Development Risk Rating Definition
68
Figure 11-2. Satellite Power System Technology Risk Assessment
69
Figure 12-1. MPTS Geometry
87
Figure 12-2. MPTS Functional Diagram
89
Figure 12-3. Beam Efficiencies (ng) for Truncated Gaussian Tapers
92
Figure 12-4. MPTS Efficiency (n) vs Frequency for Parametric Studies
95
Figure 12-5. Parametric Study Specific Costs and Weights
96
Figure 12-6. SPS Capital Cost vs Frequency - 300 $/kg
99
Figure 12-7. SPS Capital Cost vs Frequency - 100 $/kg
99
Figure 12-8. Transmitting Antenna Diameter for Lowest Cost SPS
100
Figure 12-9. Receiving Antenna Minor Axis for Lowest Cost SPS
101
Figure 12-10. Transmitting Antenna Diameter for Lowest Cost SPS (300 $/kg, 500 $/kW)
102
Figure 12-11. Receiving Antenna Minor Axis for Lowest Cost SPS (300 $/kg, 500 $/kW)
103
Figure 12-12. SPS Capital Cost for Klystron Configurations
105
Figure 12-13. Peak Ground Power Density vs Frequency
106
Figure 12-14. Receiving Antenna Size vs Beam Efficiency and Taper
108
Figure 12-15. Transmitting Antenna Size Vs Beam Efficiency and Taper
109
Figure 12-16. Peak Ground Power Density vs Beam Efficiency and Taper
110
Figure 12-17. Cost Matrix - 5 GW - Case LMM
112
Figure 12-18. Cost Matrix - 5 GW - Case MMM
113
Figure 12-19. Cost Matrix - 5 GW - Case LLH
114
Figure 12-20. Cost Matrix - 5 GW - Case HHL
115
Figure 12-21. Cost Matrix - 10 GW - Case LMM
116
Figure 12-22. Cost Matrix - 10 GW - Case MMM
117
Figure 12-23. Cost Matrix - 10 GW - Case LLH
118
Figure 12-24. Cost Matrix - 10 GW - Case HHL
119
Figure 12-25. Amplitron-Aluminum MPTS Comparison
120
Figure 12-26. Comparison of 5 GW Systems
120
Figure 12-27. SPS Capital Cost for Various Power Source Characteristics
125
Figure 12-28. SPS Energy Cost for Various Power Source Characteristics
125
Figure 12-29. SPS Energy Cost for Various Rates of Return
125
Figure 12-30. SPS Energy Cost for Various Construction Cycles
125
Figure 12-31. MPTS Cost Matrix
127
Figure 12-32. MPTS Efficiency Budget
129
Figure 12-33. Summary of Initial and Final Operational System Characteristics
131
Figure 13-1. MPTS Ground Test Functional Block Diagram
137
Figure 13-2. Instrumentation System Block Diagram
139
Figure 13-3. Ground Test Program Array Characteristics
140
Figure 13-4. Phase II Subarray - 2 x 2M - 40 kW
141
Figure 13-5. Received Power Density
142
figure 13-6. Candidate Location for Phase III Demonstration
143
Figure 13-7. Phase III Rectenna
144
Figure 13-8, Phase III Received Power
145
Figure 13-9. MPTS Ground Test Siting Profile Phase III - Goldstone
146
Figure 13-10. Technology Development and Ground Test System Schedule
149
Figure 14-1. Microwave Orbital Program
156
Figure 14-2. Geosatellite Concept
157
Figure 14-3. Five Kilowatt Geosatellite Payload
157
Figure 14-4. Geosatellite Weight Estimate and Predicted Interim Upper Stagv Performance and IUS Performance Estimate
158
Figure 14-5, Mission Schedule
159
Figure 14-6(a). Mission 2 - Structural Fabrication Technology
161
Figure 14-6(b). Mission 2 - Test Matrix
161
Figure 14-7(a). Mission 3 - Joint and Fastener Technology-
163
Figure 14-7(b). Mission 3 - Test Matrix
163
Figure 14-8(a). Mission 4 - Waveguide Fabrication Technology Sortie
165
Figure 14-8(b). Mission 4 - Test Matrix
165
Figure 14-9(a). Mission 5 - Electronics Integration
166
Figure 14-9(b). Mission 5 - Test Matrix
166
Figure 14-10(a). Mission 6 - Subassembly Build-Up
168
Figure 14-10(b). Mission 6A - Test Matrix
168
Figure 14-ll(a). Mission 7 - Rotary Joint Assembly
169
Figure 14-11(b). Mission 7 - Test Matrix
169
Figure 14-12(a). Mission 8 - Antenna to Rotary Joint Interface
171
Figure 14-12(b). Mission 8 Test Matrix
171
Figure 14-13(a)» Mission 9 - Central Mast Assembly and Integration Test
172
Figure 14-13(b). Mission 9 - Test Matrix (Conducting Mast Assembly)
172
Figure 14-14. Mission 11 - Test Matrix
175
Figure 14-15. OTF Antenna
175
Figure 14-16. OTF Power Densities
176
Figure 14-17 MPTS Orbital Test Program ROM Costs(Rough Order of Magnitude in Millions of 1975 Dollars)(Page 1 of 2)
178
Figure 14-18. Critical Technology Schedule
180
Figure 14-19. MPTS Orbital Test Program ROM Cost Summary (Rough Order of Magnitude in Millions of 1975 Dollars)
180
J-1 Total Cost Summary Format
187
J-2 Total Cost Summary - Initial Operational Systems With Minimum A(T)
189
J-3 Total Cost Summary - Operational System (Goal)
196
Figure J-4 Total Cost Summary - Initial Operational System Using
207
Figure J-5. Summary of Initial and Final Operational System Characteristics
214
Figure J-6. Capital Cost to Energy Cost Conversion versus Rate of Return
215
Figure J-7. SPS Capital Cost/ Transportation Cost for Various Power Source Characteristics
216
Figure J-8. SPS Energy Cost/Transportation Cost for Various Power Source Characteristics
217
Figure J-9. SPS Energy Cost/Transportation Cost for Various Rates of Return
218
Figure J-10. SPS Energy Cost/Transportation Cost for Various Construction Cycles
219
Figure K-l. Summary of Ground Test Objectives/Implementation
221
Figure K-2. Ionospheric Effects
223
Figure K-3. Utilization of Arecibo to Accomplish Ionosphere Test Requirements
223
Figure K-4. Ionosphere Test Requirements for F Layer
223
Figure K-5 . Power Subarray Assembly Options for Meaningful Orbital Tests
224
Figure K-6. Recommended Microwave Payload Assemblies Build-Up
224
Figure K-7 Critical Technology Required for Defined Microwave Power Ground and Orbital Test Program (Sheet 1 of 5)
225
Figure K- 8. Configurations to be Investigated on Orbit (Subarray and Below)
230
Figure K-9. Development Configuration (Subarray and Below Incorporating Control and Support Equipment)
231
Figure K-10. Large Array and Subarray Sizes for Cost. Inertia and Performance Estimation Purposes
235
Figure K- 11 Array Flight Test Hardware
241
Figure K-12. Summary of Altitude Range and Associated Power Densities
242
List of Non-Standard Terms
20
RkJQdWJsaXNoZXIy MTU5NjU0Mg==